Proposed Timetable for New Business Wing
2004 | 2005 | 2006 | 2007 | |||||||||
Phase | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 | Q4 | Q1 | Q2 | Q3 |
Fundraising (4 mo.) | ||||||||||||
Architect Selection (3 mo.) | ||||||||||||
Board of Trustees Approve Architect | 5/05 | |||||||||||
Programming Spaces (2 mo.) | ||||||||||||
Construction Manager Selection (3 mo.) | ||||||||||||
Board of Trustees Approve Contractor | 7/05 | |||||||||||
Architectural Design: (8 mo.) | ||||||||||||
Schematic Design (3 mo.) | ||||||||||||
Design Development (2 mo.) | ||||||||||||
Construction/Bid Documents (3 mo.) | ||||||||||||
Bidding and Negotiation (2 Mo.) | ||||||||||||
Awarding construction contracts | 5/06 | |||||||||||
Construction (14 mo.) | ||||||||||||
Move In (2 mo.) | ||||||||||||
Start Classes - Fall 2007 | Fa07 |