Proposed Timetable for New Business Wing

  2004 2005       2006       2007    
Phase Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
Fundraising (4 mo.)                        
Architect Selection (3 mo.)                        
    Board of Trustees Approve Architect     5/05                  
Programming Spaces (2 mo.)                        
Construction Manager Selection (3 mo.)                        
    Board of Trustees Approve Contractor       7/05                
Architectural Design: (8 mo.)                        
     Schematic Design (3 mo.)                        
     Design Development (2 mo.)                        
     Construction/Bid Documents (3 mo.)                        
Bidding and Negotiation (2 Mo.)                        
     Awarding construction contracts             5/06          
Construction (14 mo.)                        
Move In (2 mo.)                        
Start Classes - Fall 2007                       Fa07